Laser vs. Plasma vs. Oxy-Fuel Cutting Cost Calculator
Fabrication estimating tool
Laser vs. Plasma vs. Oxy-FuelCutting Cost & Time Calculator
Enter the job once. Get cut time, cycle time, material, gas, power, consumables, machine and labour cost for all three processes — then a quote price with the method you actually use. Everything recalculates as you type.
1 Job & material
Shared by all three processes. Speeds are derived from this material, thickness and machine power — override any value your machine disagrees with.
2 Laser cutting
Fibre laser module. Speed is derived from source power and thickness; replace it with your own cut-chart value at any time.
3 CNC plasma cutting
Mechanised plasma module. Consumable life is limited by whichever runs out first — pierces or arc-on hours.
4 Oxy-fuel cutting
Carbon and low-alloy steel only. Energy comes from the oxidation reaction, so thickness is limited by preheat, not by power.
5 Rates, overhead & pricing
One pricing method, one place. Pick margin or markup or multiplier — tick the double-count guards if your machine rate already carries power or labour.
Side-by-side comparison
Same job, same material cost, three process cost structures. The best supported process by cost per part is highlighted.
Cost composition
Where the money goes for the highlighted process, per part.
Cost vs. thickness
Hold this job's quantity, geometry and rates; vary thickness. The crossing point is where the cheapest process changes — not a fixed rule.
Sensitivity: margin, quantity and power price
Quote price for the highlighted process across three levers. Sanity-check a quote before you send it.
Formulas used by this calculator
Every number on screen comes from the chain below. Nothing is hidden, and nothing is added twice.
A 20% markup and a 20% gross margin do not produce the same price: at a cost of 100 the markup gives 120, the margin gives 125. This calculator keeps the two separate and shows which one is active.
Where the cutting speeds come from
Laser and plasma speeds here are generic planning estimates, derived from a power/amperage-versus-thickness relationship, not copied manufacturer cut charts. Oxy-fuel uses a thickness-banded interpolation table because its speed curve is not a simple power law. Real speed depends on machine power, gas, nozzle, focus, consumable condition and material grade, so manufacturer charts take priority over anything shown here. That is why each speed field has an auto override and why the report marks whether a value was estimated or entered by you.
What this tool deliberately does not do
- It does not claim one universal speed table fits every machine, or that thickness alone decides the winning process.
- It does not price secondary operations it cannot see — grinding, machining allowances, heat-treatment, painting.
- It does not import DXF geometry. Enter cut length, pierce count and part area from your CAM system, where they are accurate.
How to use it
- Quick estimate: material, thickness, cut length, quantity and your machine rates. Enough for a phone quote in under a minute.
- Detailed: adds consumables, gas pricing, setup, handling and finishing — the terms that actually decide whether a small job is profitable.
- Advanced: exposes pierce time, kerf, arc voltage, corner allowances and rapid travel so you can match measured machine behaviour.
- Set the Double-count guards before trusting a rate. If your machine rate already includes power or the operator, tick those boxes or the cost is counted twice.
- Use Copy full report for a text handoff, CSV for a spreadsheet, and Print / PDF for a customer-facing sheet.
Frequently asked questions
Is laser or plasma cheaper?
There is no universal answer. Laser usually wins on thin sheet, tight tolerance and high volume per part; plasma usually wins on thick plate, loose tolerance and lower capital cost; oxy-fuel is the only productive option for very thick carbon steel, roughly beyond 50–75 mm, and the cheapest per metre at those thicknesses. The comparison table ranks by your job's actual cost per part, not by a thickness rule of thumb.
Why is my calculated cut time shorter than the machine's?
Because published speeds assume ideal conditions. Corners, acceleration, leads, micro-joints, dross and pierce delays add time. Raise the corner/accel allowance in Advanced mode, or enter the cycle time your machine actually reports and back-calculate the effective speed.
Why does the calculator warn about laser and copper or brass?
Those metals reflect the near-infrared beam of a fibre laser, so coupling is poor and the risk of back-reflection damage to the source is real. They are cuttable with the right source and settings, but a generic estimate is not trustworthy — treat it as a flag, not a price.
Why is oxy-fuel marked unsupported for stainless and aluminium?
Oxy-fuel cutting relies on iron oxidising and being blown out of the kerf. Stainless forms a refractory chromium oxide that resists the jet, and aluminium's oxide melts far above the metal. Neither is a routine oxy-fuel job; plasma or laser take them.
How do I use my own cut chart?
Enter the speed in mm/min (or ipm in imperial mode) in the process's speed field. The value locks in, the auto button switches to manual, and the report records it as a user-entered value instead of an estimate.
What is the difference between cost per part and cost per metre?
Cost per part includes material, setup and handling. Cost per metre is a process rate: cut, gas, power, consumables and machine time per metre of cut. Mixing material into a per-metre figure makes two processes look different when only the material is the same. Both are shown separately.
Can I trust the quote price?
It is a defensible arithmetic result from your inputs, not a market price. Check the margin method, the overhead percentage and whether scrap credit is realistic before sending it. The cost vs. thickness chart and the sensitivity table exist so you can see how fragile the number is.
Does anything leave my browser?
No. All calculation, saving and export happen locally in the page. Saved scenarios use your browser's local storage, so they stay on your machine and disappear if you clear site data.
Laser vs Plasma vs Oxy‑Fuel Cutting Cost Calculator — Complete User Guide
This guide walks you through every field of the SteelSolver.com Laser vs Plasma vs Oxy‑Fuel Cutting Cost Calculator. You will learn what each input controls, which units to use, how the cost model works behind the scenes, and how to avoid the mistakes that make a quote lose money. By the end you will be able to produce a defensible cost‑per‑part and a customer‑ready quote in under a minute.
What Is This Calculation Used For?
Thermal cutting cost estimation answers a single commercial question: what does it actually cost me to produce one part, and what should I charge for it? The calculator builds that answer from the ground up — geometry, machine time, consumables, gas, power, labour and overhead — for three competing processes on the same job.
Where Engineers and Estimators Apply It
| Application | What the Calculator Delivers |
|---|---|
| Fabrication quoting | Direct cost per part, batch direct cost, quote price per part, net margin, and profit per batch. |
| Process selection | Side‑by‑side cost and cycle time for laser, plasma and oxy‑fuel on the same geometry. |
| Make‑or‑buy decisions | All‑in cost per metre and cost per part that can be compared with an external supplier's price. |
| Break‑even analysis | Cost‑vs‑thickness chart showing where the cheapest process changes for your rates. |
| Sensitivity checking | Quote price across margin, batch quantity and electricity price before the quote is sent. |
| Consumable budgeting | Nozzle, window, electrode and tip consumption per job, priced at your replacement cost. |
Real‑World Usage
A job shop receives a request for 50 brackets in 6 mm mild steel with 1,800 mm of cut and 6 pierces per part. The estimator enters the geometry once, reads the three process costs, and immediately sees whether laser or plasma is cheaper at that thickness for the shop's own machine rates. The sensitivity table then shows what happens to the quote price if the customer doubles the quantity — often the difference between a profitable and a marginal order.
Step‑by‑Step Guide to Every Field
The calculator is organised into five numbered cards. Work through them in order — each card builds on the one before. The Quick / Detailed / Advanced toggle at the top controls how many fields are visible: start in Quick, switch to Detailed when you need consumable and labour detail, and use Advanced only when matching measured machine behaviour.
Step 1 — Job & Material
These inputs are shared by all three processes. Everything downstream — speed, gas use, material mass — is derived from them, so get them right first.
| Field | Unit | What It Does & How to Fill It |
|---|---|---|
| Material family | — | Selects density and the process suitability factors. Mild steel, stainless, aluminium, galvanised, alloy, copper, brass and cast iron are supported. Copper and brass trigger a laser back‑reflection warning. |
| Grade | — | Recorded in the report only. Speed and cost use the material family, because cut charts are published per family, not per grade. |
| Thickness | mm / in | Plate thickness. Drives cutting speed, material mass and every process‑suitability warning. Must be greater than 0.3 mm. |
| Density | kg/m³ | Read‑only. Looked up from the material family and shown so you can verify it against your stock certificate. |
| Sheet length / width | mm / in | Raw sheet size. Used to sanity‑check nesting and for the report header. |
| Part length / width | mm / in | The bounding rectangle of the part. Used to compute part area and therefore material mass per part. |
| Cut length / part | mm / in | Total tool path: all outer contours, holes and slots, excluding lead‑ins. Take this from your CAM system — it is the single most important time driver. |
| Pierce points / part | count | Number of pierces per part. Each pierce costs time (and for plasma, consumable life) even if it never moves in X‑Y. |
| Quantity (parts) | count | Batch size. Setup and programming are spread across this number, so small batches look very different from large ones. |
| Nesting efficiency | % | Usable share of the sheet. 100 % means perfect tiling; real nests typically lose 10–20 % to skeleton and edge trim. Values below 70 % raise material cost steeply. |
| Material price | /kg or /lb | Mill or stockist price for sheet weight. Applies to the effective area (part area ÷ nesting efficiency). |
| Remnant / scrap credit Adv | % | Discount on material cost for reusable offcuts. Above 30 % is optimistic unless you actually resell or reuse the skeleton. |
| Load / unload per part Det | min | Manual handling time per part. Added to cycle time before labour cost is calculated. |
| Setup + programming / batch Det | min | One‑off time per batch. Dominates small‑batch economics — watch it in the sensitivity table. |
| Deburr / dross removal per part Det | min | Finishing time per part, priced at the finishing labour rate. This is where plasma dross and oxy‑fuel slag show up. |
| Finishing labour rate Det | /h | Hourly rate for the finishing operation. Kept separate from the machine operator rate. |
| Rapid traverse speed Adv | mm/min or in/min | Machine rapid speed. Used to convert rapid distance into non‑cutting cycle time. |
| Rapid distance / part Adv | mm / in | Total rapid travel per part. A measured value from the machine is better than a guess. |
Step 2 — Laser Cutting
The laser module derives cutting speed from source power and thickness. Every auto‑generated value can be overridden with your own cut‑chart number by typing in the field — the auto button then switches to manual and the report records it as user‑entered.
| Field | Unit | What It Does & How to Fill It |
|---|---|---|
| Laser type | — | Fibre or CO₂. CO₂ is derated to 60 % of fibre speed to reflect real‑world cutting rates. |
| Source power | kW | Rated laser power. The generic model scales speed with power0.9 ÷ thickness1.1. |
| Cutting speed | mm/min or in/min | Auto‑generated from power and thickness. Override with the manufacturer's chart value — the field locks to manual and the report flags it. |
| Machine rate | /h | Ownership, depreciation, floor space, maintenance and servicing per productive machine hour. Excludes gas, power, consumables and labour unless you tick the double‑count guards in Step 5. |
| Assist gas | — | N₂, O₂ or compressed air. O₂ increases speed by 35 %; air reduces it by 15 % in the generic model. |
| Gas flow | m³/h | Nozzle flow rate. Multiplied by arc‑on hours to give gas volume, then by gas price. |
| Gas price | /m³ | Your delivered gas cost. N₂ is typically the most expensive assist gas. |
| System power draw | kW | Whole‑system draw: source, chiller, extraction, servos. Auto‑computed as 2.6 × power + 5 kW; override with a measured value. |
| Nozzle price / life Det | /h | Replacement cost and expected life. Consumable cost per hour = price ÷ life. |
| Protective window price / life Det | /h | Same logic as the nozzle. Both are charged per arc‑on hour. |
| Pierce time Adv | s/pt | Auto‑generated from power and thickness. Override with a measured pierce time. |
| Kerf width Adv | mm | Reported for reference. Does not change cost directly in the quick model. |
| Corner / accel. allowance Adv | % | Multiplier on cut + pierce + rapid time to account for corners, acceleration and lead‑ins. 6–10 % is typical for fibre laser. |
Step 3 — CNC Plasma Cutting
Plasma speed depends on output current, thickness and plasma gas. Consumable life is limited by whichever runs out first: pierces or arc‑on hours.
| Field | Unit | What It Does & How to Fill It |
|---|---|---|
| Output current | A | 45–400 A. Drives speed via current0.55 ÷ thickness1.15. A capacity warning fires when thickness exceeds 0.16 × amps. |
| Cutting speed | mm/min or in/min | Auto‑generated. Override with your cut‑chart value to lock it to manual. |
| Machine rate | /h | Plasma table rate. Same double‑count logic as the laser. |
| Plasma gas | — | Air, O₂ or N₂. O₂ increases speed by 25 %; N₂ reduces it by 5 %. |
| Gas flow | L/min | Torch flow. Converted to m³/h (× 0.06) before multiplying by gas price and arc‑on hours. |
| Gas price | /m³ | Compressed air is often priced at zero if it comes from a shop compressor; O₂ and N₂ are charged per m³. |
| Power draw | kW | Arc power plus supply and torch‑cooling losses. Auto‑computed as amps × volts ÷ 1000 × 1.45; override with a measured value. |
| Arc voltage Adv | V | Used only in the auto power‑draw calculation. Enter the value from your cut chart. |
| Consumable set price Det | — | Electrode + nozzle + shield + swirl ring as one set. |
| Set life (pierces) Det | count | Number of pierces the set survives. Pierce count per job = pierces × quantity. |
| Set life (arc‑on) Det | h | Arc‑on hours the set survives. The calculator charges whichever limit binds first. |
| Pierce delay Adv | s/pt | Auto‑generated as 0.09 × thickness + 0.2 s. Override with a measured value. |
| Kerf width Adv | mm | Reported for reference. |
| Corner / accel. allowance Adv | % | Multiplier on cycle time. 5–8 % is typical for a well‑tuned plasma table. |
Step 4 — Oxy‑Fuel Cutting
Oxy‑fuel is supported for carbon and low‑alloy steel only. The calculator marks stainless, aluminium, copper and brass as unsupported rather than pricing them — that keeps the comparison honest.
| Field | Unit | What It Does & How to Fill It |
|---|---|---|
| Fuel gas | — | Acetylene, propane or natural gas. Changes only the fuel price line, not the speed. |
| Cutting speed | mm/min or in/min | Auto‑generated from a thickness‑banded interpolation table, because the oxy‑fuel speed curve is not a simple power law. Override with your chart value. |
| Machine / torch rate | /h | Table or torch station rate. |
| Oxygen flow | m³/h | Cutting oxygen flow. Multiplied by arc‑on hours and oxygen price. |
| Fuel flow | m³/h | Fuel gas flow. Multiplied by arc‑on hours and fuel price. |
| Oxygen price | /m³ | Delivered oxygen cost. Oxy‑fuel jobs are oxygen‑intensive, so this line matters. |
| Fuel price | /m³ | Delivered fuel gas cost. Acetylene is usually the most expensive. |
| Preheat per pierce | s | Auto‑generated as 2 + 0.35 × thickness seconds. Override with a measured value. |
| Cutting tip price / life Det | /h | Replacement cost and expected life. Consumable cost per hour = price ÷ life. |
| Kerf width Adv | mm | Reported for reference. |
| Handling allowance Adv | % | Multiplier on cycle time. 4–6 % is typical for a straight‑line oxy‑fuel cut. |
Step 5 — Rates, Overhead & Pricing
One pricing method, one place. Pick margin or markup or multiplier — never two at once. Tick the double‑count guards if your machine rate already carries power or labour.
| Field | Unit | What It Does & How to Fill It |
|---|---|---|
| Electricity | /kWh | Your industrial tariff. Multiplied by system draw and operating hours. Ignored if the power‑in‑rate guard is ticked. |
| Operator rate | /h | Fully burdened labour rate. Multiplied by (cycle + handling) × quantity. Ignored if the labour‑in‑rate guard is ticked. |
| Overhead | % | Percentage added to direct cost before pricing. Covers rent, admin, insurance and non‑productive labour. |
| Pricing method | — | Gross margin, markup, or multiplier. The label and unit symbol update automatically. |
| Margin / markup / multiplier | % or × | The single pricing lever. A 20 % markup and a 20 % margin are not the same price — the calculator keeps them separate. |
| Tax / VAT on quote | % | Added to the quote total after margin. Set to zero if your quotes are tax‑exclusive. |
| Minimum order charge Det | /order | Floor on the batch quote. Useful for one‑off or sample jobs. |
| Rush surcharge Det | % | Multiplier on the quote total for expedited delivery. |
| Power already in machine rate | checkbox | Tick if your machine rate includes electricity. Prevents double charging. |
| Labour already in machine rate | checkbox | Tick if your machine rate includes the operator. Prevents double charging. |
Visual: How the Cost Model Fits Together
The diagram below shows the flow from raw inputs to the final quote. Material cost is shared by all three processes; the process‑specific branches differ only in time, gas, power and consumable structure.
Figure 1 — Cost model flow. The shared material cost is computed once; each process branch adds its own time‑dependent and consumable‑dependent costs before combining into the direct cost and quote price.
Worked Example — 6 mm Mild Steel Bracket
This is the sample job built into the calculator. Follow it once to see how every line is produced, then substitute your own numbers.
Inputs
- Material: mild steel (ASTM A36), density 7,850 kg/m³
- Thickness:
6 mm - Part:
300 mm × 200 mm= 0.06 m² - Cut length:
1,800 mmper part - Pierce points:
6per part - Quantity:
50parts - Nesting efficiency:
82 % - Material price:
$1.20/kg - Laser:
6 kWfibre, N₂ assist at 25 m³/h, machine rate $32/h - Plasma:
105 Aair, machine rate $22/h - Oxy‑fuel: acetylene, machine rate $14/h
- Labour:
$22/h, overhead12 %, margin25 %
Step‑by‑Step Calculation
1. Material cost per part
2. Laser cycle time
3. Laser cost per part
4. Quote price per part
5. Result
At 6 mm mild steel with these rates, the laser produces the lowest direct cost per part. Plasma and oxy‑fuel are priced on the same material cost but with different time, gas and consumable structures. Open the Cost vs. thickness chart to see where the ranking changes for your rates.
Key User Pain Points and How This Calculator Solves Them
Cutting cost estimation fails in predictable ways. The table below lists the pain points estimators actually report, and the specific mechanism in the calculator that addresses each one.
| Pain Point | Why It Hurts | How the Calculator Solves It |
|---|---|---|
| Double‑counting power and labour | Machine rates often already include electricity and operator cost. Adding them again inflates the quote and loses the job — or hides a real loss. | The two double‑count guards in Step 5 remove power or labour from the calculation when they are already in the machine rate. The warnings panel confirms which guards are active. |
| Mixing markup and margin | A 20 % markup and a 20 % margin produce different prices. Using the wrong one silently erodes profit. | Step 5 keeps margin, markup and multiplier as three separate methods. The label and unit symbol update automatically, and the formula panel shows which one is active. |
| Ignoring consumable life | Nozzles, windows, electrodes and tips are a real hourly cost. Omitting them makes plasma look cheaper than it is. | Detailed mode adds nozzle, window, electrode set and tip life. Plasma consumables are charged by whichever binds first — pierces or arc‑on hours. |
| Wrong cut length | Using the part outline instead of the full tool path underestimates cut time, sometimes by a factor of three. | The cut length field is labelled as the total tool path and the warning panel flags high pierce density. The report records the value used so it can be checked against CAM. |
| Guessing cutting speed | Every machine and material is different. A generic speed table can be 30–50 % off. | Every speed field has an auto override. Typing a value locks it to manual, the field turns orange, and the report marks it as user‑entered rather than estimated. |
| Small‑batch setup shock | Setup and programming dominate the cost of a 5‑part order, but the quote is often based on the per‑part run cost alone. | Setup minutes are spread across the batch and shown on their own line. The sensitivity table shows quote price at quantities 1, 10, 25, 50, 100 and 250. |
| Comparing unlike numbers | Cost per metre and cost per part measure different things. Mixing material into a per‑metre figure makes two processes look different when only the material is the same. | The comparison table shows process cost per metre (excluding material and setup) and all‑in cost per metre as separate rows, alongside cost per part. |
| Unsupported material silently priced | Oxy‑fuel cannot cut stainless or aluminium economically. Pricing it anyway gives a false comparison. | Oxy‑fuel is marked unsupported for stainless, aluminium, copper and brass rather than priced. The reason is shown in the warnings panel. |
| Quote price that is not defensible | A number is not a quote unless you can show where it came from. | Copy full report produces a text breakdown with every cost line. CSV exports the same table for a spreadsheet. Print / PDF produces a customer‑facing sheet. |
Input Validation and Unit Handling
Every numeric field is validated on input. Values that would produce nonsense — negative thickness, zero quantity, nesting above 100 % — are clamped to a safe range before the calculation runs, so the calculator never shows a misleading result.
Validation Rules
- Thickness — minimum 0.3 mm (0.012 in). Values below this are clamped.
- Quantity — minimum 1 part. Decimals are rounded to the nearest whole part.
- Nesting efficiency — clamped between 1 % and 100 %.
- Scrap credit — clamped between 0 % and 90 %.
- Rapid speed — minimum 100 mm/min; auto‑generated values respect this floor.
- Consumable life — minimum 0.1 h or 1 pierce, so a divide‑by‑zero cannot occur.
- Margin — clamped at 95 %, because a 100 % gross margin requires an infinite price.
- Multiplier — minimum 0.1 ×, so the quote cannot be zero.
- Tax — clamped between 0 % and 50 %.
- Rush surcharge — clamped between 0 % and 100 %.
Unit Handling
The Metric / Imperial toggle converts every length, thickness, speed and mass‑price field at once. The conversion factors are exact: 25.4 mm per inch and 2.2046226 lb per kilogram. Fields display the correct unit label and the correct number of decimal places for the active system. Internally, all calculations run in metric, so switching units never changes the result — only the display.
Common Mistakes to Avoid
Data Entry Mistakes
- Using part perimeter instead of cut length. Include every hole and slot — the value should come from CAM, not from the drawing outline.
- Leaving pierce count at zero. A part with holes has pierces. Zero pierces understates cycle time and overstates plasma consumable life.
- Entering sheet size instead of part size. The part length and width are the bounding rectangle of the finished part, not the raw sheet.
- Forgetting the remnant credit. If you actually resell or reuse offcuts, a 0 % credit overstates material cost and makes every process look worse than it is.
- Setting nesting to 100 %. Perfect tiling is a theoretical limit, not a real nest. 80–85 % is a realistic shop value.
Rate and Pricing Mistakes
- Ticking both double‑count guards and then adding labour again. The guard removes labour entirely — pick one approach and stick to it.
- Using markup where margin was intended. At a cost of 100, a 20 % markup gives 120 and a 20 % margin gives 125. The two are not interchangeable.
- Leaving overhead at zero. Overhead is real — rent, admin, insurance and non‑productive labour do not disappear because they are not on the machine.
- Ignoring the minimum order charge. For a one‑off part, setup can dominate. The minimum charge is a floor, not a suggestion.
Process Selection Mistakes
- Assuming thickness alone decides the winner. The crossing point depends on your machine rates, gas prices, labour rate and batch size. Use the cost‑vs‑thickness chart, not a rule of thumb.
- Pricing oxy‑fuel for stainless or aluminium. The calculator marks it unsupported for a reason — those materials form refractory oxides that resist the oxy‑fuel jet.
- Ignoring the plasma capacity warning. When thickness exceeds 0.16 × amps, quality falls sharply. The estimate is still arithmetically correct, but the process may not be commercially viable.
- Treating the auto speed as a cut chart. It is a planning estimate. Manufacturer charts and measured shop data always take priority.
Frequently Asked Questions
Is laser or plasma cheaper for my job?
There is no universal answer. Laser usually wins on thin sheet, tight tolerance and high volume per part; plasma usually wins on thick plate, loose tolerance and lower capital cost. The comparison table ranks by your job's actual cost per part, using your machine rates, gas prices and labour rate — not by a thickness rule of thumb. Change one rate and the ranking can flip, which is why the sensitivity table exists.
Why is my calculated cut time shorter than the machine's?
Published speeds assume ideal conditions. Corners, acceleration, leads, micro‑joints, dross and pierce delays all add time. Raise the corner / acceleration allowance in Advanced mode, or enter the cycle time your machine actually reports and back‑calculate the effective speed. The allowance is a multiplier on cut + pierce + rapid time, so a 10 % allowance adds 10 % to the total.
Why does the calculator warn about laser and copper or brass?
Those metals reflect the near‑infrared beam of a fibre laser, so coupling is poor and the risk of back‑reflection damage to the source is real. They are cuttable with the right source and settings, but a generic estimate is not trustworthy — treat the laser figure as a lower bound on cost, not a price.
Why is oxy‑fuel marked unsupported for stainless and aluminium?
Oxy‑fuel cutting relies on iron oxidising and being blown out of the kerf. Stainless forms a refractory chromium oxide that resists the jet, and aluminium's oxide melts far above the metal. Neither is a routine oxy‑fuel job; plasma or laser take them. Marking oxy‑fuel unsupported rather than pricing it keeps the comparison honest.
How do I use my own cut chart?
Enter the speed in mm/min (or in/min in imperial mode) in the process's speed field. The value locks in, the auto button switches to manual, and the report records it as a user‑entered value instead of an estimate. The same override works for pierce time, preheat time and power draw.
What is the difference between cost per part and cost per metre?
Cost per part includes material, setup and handling. Cost per metre is a process rate: cut, gas, power, consumables and machine time per metre of cut. Mixing material into a per‑metre figure makes two processes look different when only the material is the same. The comparison table shows both separately, alongside an all‑in cost per metre that does include material.
Can I trust the quote price?
It is a defensible arithmetic result from your inputs, not a market price. Check the margin method, the overhead percentage and whether the scrap credit is realistic before sending it. The cost‑vs‑thickness chart and the sensitivity table exist so you can see how fragile the number is before a customer sees it.
Does anything leave my browser?
No. All calculation, saving and export happen locally in the page. Saved scenarios use your browser's local storage, so they stay on your machine and disappear if you clear site data. There is no backend, no account and no tracking.
How do I export a quote for a customer?
Use Copy full report for a text handoff, CSV for a spreadsheet, and Print / PDF for a customer‑facing sheet. The print layout hides the controls and shows only the summary, comparison table, breakdown and warnings.
Which standards does the calculator follow?
The calculator is an estimating tool, not a code‑compliance calculator. It does not check AISC, ASCE or Eurocode requirements — those apply to structural design and connection capacity, not to cutting cost. What it does follow is the standard cost‑estimation convention: direct cost plus overhead, then a separate pricing method, with power and labour tracked separately so they can be included or excluded without double counting.
Engineering Explanation of the Cost Model
Time Model
Cycle time is the sum of cut time, pierce time and rapid time, multiplied by a process‑specific allowance for corners and acceleration. Cut time is cut length divided by cutting speed. Pierce time is pierce count times pierce time per point, divided by 60 to convert seconds to minutes. Rapid time is rapid distance divided by rapid speed. The allowance multiplier is the only place where machine dynamics are represented — it is a single number that captures acceleration, deceleration, lead‑ins and corner slowdowns.
Material Model
Material cost per part is the effective sheet area times thickness times density times price, less any remnant credit. Effective area is part area divided by nesting efficiency — the fraction of the sheet that the nest actually uses. This is why nesting efficiency has such a large effect on cost: at 70 % efficiency the material cost per part is 43 % higher than at 100 %.
Consumable Model
Laser consumables (nozzle and protective window) are charged per arc‑on hour: replacement price divided by expected life. Plasma consumables are charged by whichever binds first — the number of pierces divided by set life in pierces, or the number of arc‑on hours divided by set life in hours. Oxy‑fuel tips are charged per arc‑on hour. This is why plasma pierce count has a direct cost consequence that laser pierce count does not.
Pricing Model
Direct cost is the sum of material, machine, power, gas, consumables, labour, finishing and setup. Overhead is applied as a percentage of direct cost. The pricing method then converts the overheaded base into a quote price: gross margin divides by (1 − margin), markup multiplies by (1 + markup), and multiplier multiplies by the multiplier itself. Tax, rush surcharge and minimum charge are applied after pricing, in that order.
More Examples
Example 2 — 20 mm Mild Steel Plate, 10 Parts
At 20 mm, plasma and oxy‑fuel both become competitive with laser. The cost‑vs‑thickness chart will show the crossing point. Set quantity to 10 and watch the setup line grow as a share of the quote — this is where the minimum order charge earns its place.
Example 3 — 2 mm Stainless Steel, 200 Parts
Thin stainless is a laser job. Plasma dross on thin stainless is heavy, and oxy‑fuel is unsupported. Enter the laser speed from the manufacturer's chart for 2 mm 304, set nesting to 85 %, and compare the quote at quantity 200 against quantity 50 — the setup line almost disappears, and the per‑part price drops accordingly.
Example 4 — 50 mm Mild Steel, 5 Parts
At 50 mm, oxy‑fuel is the only productive option for many shops. The plasma capacity warning will fire at 105 A. The laser warning will fire because 6 kW is low for 50 mm. Use the oxy‑fuel branch and enter your torch's measured speed — the generic table is a planning value, not a chart.
Before You Send the Quote — Final Checklist
- Cut length and pierce count came from CAM, not from the drawing outline.
- Nesting efficiency reflects a real nest, not a theoretical tiling.
- Machine rates match the machines that will actually run the job.
- Double‑count guards match whether power and labour are already in the machine rate.
- Pricing method is the one your business actually uses — margin, markup or multiplier.
- Overhead is a real number, not zero.
- Scrap credit is realistic — if you do not resell offcuts, leave it at zero.
- Sensitivity table checked at the quantity the customer actually asked for.
- Warnings panel read — every note is there for a reason.
- Report copied or printed so the number can be defended if challenged.
SteelSolver.com — engineering tools for fabrication estimating. This guide is part of the cutting cost calculator documentation. The calculator itself is an estimating tool; manufacturer cut charts and measured shop data always take priority over generic planning values.